Workflow rules and behaviour

  • Duration of Workflows is flexible and you can change it by rescheduling, if permitted
  • Content Manager re-calculates Workflow due date and time when
    • an estimated duration changes
    • a user adds or removes an Activity
  • An Activity should not be assigned to a Group with the Activity Properties - Option tab option Automatically complete once started selected.

    If you need to select the option, the Activity should be assigned to a Supervisor.

  • Content Manager is designed to have only one last activity for each Workflow, otherwise an error message will display and a pseudo last activity will be created to make the Workflow valid. In terms of rollback functionality, you can only rollback to an activity's predecessor activities. If you design rollback steps correctly, there is no need to create a pseudo activity.