Workflow Activity Progress page
Schedule
- Earliest Start Date - this is the earliest date that the Activity was actually started
- Latest Start Date - date the Activity was last started, for example after an Uncomplete
- Estimated Duration - time between start date and due date
- Date Due - when the Activity is due to be completed
Status
- Currently - displays the current Activity status
- Not Ready to Start - cannot be started, e.g. start conditions are not met
- Ready to Start - can be started
- Started - has been started or made Uncomplete
- Suspended - has been started and suspended, or another earlier Activity is suspended
Suspended until - date and time suspension ends
- Ready To Resume - suspension has elapsed, can now be resumed again
- Finally Completed - has been completed
Final Completion Date - date and time completed