The following details the tabs on the Task Editor.
To assign tasks to available resources, select one or more available users and click Add selected users to add them to the Task resource assignments list. Click Remove selected users to remove selected users from the list.
The Time tab automatically tracks the variance between the estimated and actual start date, finish date, and duration of a task.
| Property | Description |
|---|---|
| Plan Start | Estimated start date for the task. The default value is the current date. |
| Plan Finish | Estimated finish date for the task. The default value is the current date. |
| Plan Work | Number of hours estimated to complete the task. |
| Actual Start | Actual start date calculated from work records. |
| Actual Finish | Actual finish date when the task status changes to Finished. |
| Actual Work | Actual number of hours taken to complete the task, calculated from work records. |
| Variance Start | Variance in days between the expected start date and the actual start date. This value is a read-only calculated value. |
| Variance Finish | Variance in days between the expected finish date and the actual finish date. This value is a read-only calculated value. |
| Variance Work | Variance in number of hours between estimated and actual duration. This value is a read-only calculated value. |
| User Name | Name of the person who performed the work for this work-record entry. The default value is the current user. |
| Date | Date work was done for this work record. The default value is the current date. |
| Work | Number of hours worked for this work-record entry. |
| Remaining Work | Remaining number of hours to complete the task. |
| Comments | Field used to provide additional information about what work was done for this work record. |