Creating a Baseline for a Caliber-Integrated Project

To create a baseline of a Caliber-integrated Silk Central project:

  1. Create a baseline of the Silk Central project. A Silk Central message box displays during the process, asking if you want to enable the Caliber integration for the new baseline.
  2. Click Yes. When the new baseline is created, the Baseline Project - Adapt Project Settings dialog box opens.
  3. Click Edit to change the requirements integration settings.

    The Edit Configuration dialog box opens.

  4. Click Browse next to the Project name field. The Browse Projects dialog box opens.
  5. Select a Caliber project, a baseline, and the requirement type for synchronization.
  6. Click Ok to close the Browse Projects dialog box.
  7. Click Ok to close the Edit Configuration dialog box.
  8. Click Finish to close the Baseline Project - Adapt Project Settings dialog box.