Displaying Performance Level Conditions

Before you can display performance levels in charts, you have to define and assign them. You can do so before a load test execution (proactive approach) or after an execution (reactive approach).

To display performance level conditions in a chart:

  1. Create or open a chart.
  2. Drag measures that have performance levels assigned onto the chart.
  3. Click a measure in the measure list to activate it.
  4. On the Series tab, in the Display group, enable Performance Level Conditions.
The chart shows colored boundaries for the conditions of the assigned performance level and a small legend describing them. For example: If the current performance level contains a condition like P90 < 0.2, the condition is fulfilled if 90 % of the graph lie below the shown boundary.
Note: Performance Explorer only shows performance level conditions for one measure at a time.