Comparing a Project with a Baseline

For baselined projects, you can use the Baseline Comparison report to see all the changes to the tests in the project since the moment the project was baselined.

To view the report:

  1. In the menu, click Projects > Project List.
  2. Use Ctrl+Click to select the project and the baseline of the project that you want to compare.
    Tip: For easier selection of the baselines, don't click on the name of the baseline. Click into another column instead.
  3. Right click on the selection.
  4. Select Reports > Baseline Tests Comparison .
    Note: The Baseline Comparison report must be executed once to display in the context-menu. If the report is grayed out, execute the report once in the Reports area.