Adding Definite Runs

Note: You must have administrator rights to edit global schedules. To define a definite run for a global schedule, navigate to Administration > Schedules.

To add a definite run to a custom schedule:

  1. In the menu, click Execution Planning > Details View.
  2. Select the execution plan, folder, or configuration suite, for which you want to add a definite run.
  3. Click the Schedule tab.
  4. Click the Custom option to enable the scheduling controls.
  5. Click Add Definite Run.
  6. On the Configure Definite Run page, click Edit and select the date and time when the execution plan, folder, or configuration suite, should definitely be run.
  7. Click OK. Your definite run settings are listed on the Schedule page.
  8. Click Save to add the definite run to the current schedule, or continue adding definite runs.